2003 PAVED ROAD SCHEDULE

(tentative)

1. Reclaim Pavement (grind in place) - June 23 – July 11

Miller Rd. (Airport Rd. to southerly

Birchwood Park), East Balsam

2. Paving Contract #1 - July 14 – 25

Miller Rd. (Airport Rd. to southerly

Birchwood Park), East Balsam,

Osborne Road

  1. Cold Mix Paving, Chip Seal – July 27 – Aug. 8

Plainfield Brook Rd. (end of pavement

To mid-section)

4. Milling Asphalt (grind off, haul away) - Aug. 11 – 22

Little John Rd., Gregoire St., 600’ on Brook St.,

W. Cobble Hill (from Hill St. to Tamarack),

Donahue Rd. (from Drury Hill to sharp curve)

5. Paving Contract # 2 - Aug. 25 – Sept. 12

Donahue Rd., W. Cobble Hill, Rudd Farm,

Daniels Drive

6. Paving Contract # 3 - Sept. 15 – 26

Little John Rd. (Church Hill to end of

pavement), Gregoire St., Sabett, Brook St.,

Libercent, Violette, Casanova, Milano Hill