2003 PAVED ROAD SCHEDULE
(tentative)
1. Reclaim Pavement (grind in place) - June 23 – July 11
Miller Rd. (Airport Rd. to southerly
Birchwood Park), East Balsam
2. Paving Contract #1 - July 14 – 25
Miller Rd. (Airport Rd. to southerly
Birchwood Park), East Balsam,
Osborne Road
Plainfield Brook Rd. (end of pavement
To mid-section)
4. Milling Asphalt (grind off, haul away) - Aug. 11 – 22
Little John Rd., Gregoire St., 600’ on Brook St.,
W. Cobble Hill (from Hill St. to Tamarack),
Donahue Rd. (from Drury Hill to sharp curve)
5. Paving Contract # 2 - Aug. 25 – Sept. 12
Donahue Rd., W. Cobble Hill, Rudd Farm,
Daniels Drive
6. Paving Contract # 3 - Sept. 15 – 26
Little John Rd. (Church Hill to end of
pavement), Gregoire St., Sabett, Brook St.,
Libercent, Violette, Casanova, Milano Hill